Golticlay Wind Farm
Golticlay Wind Farm is a wind, solar and storage project tracked on slava.it.com. The archive holds 4 community posts from 2 groups, latest 2026-10-02. 7 register records are listed (4 REPD, 3 NESO Embedded). Their statuses differ, so no single status is given. Top recurring themes: Onshore Wind (3). Posts are archived public group posts and are not independently verified.
Facts and where they come from
Basis: register = taken from a public register (dates and licences are under Data credits).
Abbreviations: REPD = Renewable Energy Planning Database; NESO = National Energy System Operator.
| Item | Value | Basis |
|---|---|---|
| Register records | 7 listed (4 REPD, 3 NESO Embedded). Statuses: Planning Application Submitted (2), Awaiting Consents (2), Under Construction (1), No Application Required (1), Scoping (1) | register |
Register records
Each row is one register record with its own identifier; records are not combined. Relationships are stated only where a register links the records, and are otherwise labelled as unlinked or unverified. REPD dates are the record's update date and the date of the status event where one is recorded. The NESO files give no status date; the date shown is the MW effective-from date.
| Register | Identifier | Name as recorded | Status | Capacity | Date | Relationship |
|---|---|---|---|---|---|---|
| REPD | 5195 | Golticlay Wind Farm | Under Construction | 72.6 MW | record updated 2026-02-23; status event 2025-07-01 | Exact name match. |
| REPD | 20387 | Golticlay Wind Farm 2 | No Application Required | 13.2 MW | record updated 2026-02-23 | 'Golticlay Wind Farm 2'; the REPD file gives it the same map reference as 5195; no identifier link. |
| REPD | 18325 | Golticlay Wind Farm, Bulreanrob - Wind Farm | Planning Application Submitted | not recorded | record updated 2026-01-09; status event 2025-12-03 | Bulreanrob wind farm record; REPD links 18325 and 18326 to each other, not to 5195. |
| REPD | 18326 | Golticlay Wind Farm, Bulreanrob - Battery Energy Storage | Planning Application Submitted | not recorded | record updated 2026-01-09; status event 2025-12-03 | Bulreanrob battery storage; REPD links it to 18325 (storage co-location). |
| NESO Embedded | PRO-000370-1 | Golticlay Wind Farm | Awaiting Consents | connected 0 MW; cumulative 50.07 MW | MW effective from 2026-07-31 | Stage 1 of NESO project PRO-000370 (Embedded Register); same name as REPD 5195 but capacity differs and no identifier is shared, so the link is unverified. |
| NESO Embedded | PRO-000370-2 | Golticlay Wind Farm | Scoping | connected 0 MW; cumulative 58 MW | MW effective from 2026-07-31 | Stage 2 of NESO project PRO-000370. |
| NESO Embedded | PRO-000926 | Golticlay Extension Wind Farm | Awaiting Consents | connected 0 MW; cumulative 55 MW | MW effective from 2027-09-30 | 'Golticlay Extension Wind Farm'; a different NESO project number; relation to the REPD records is unverified. |
Data credits
- Contains public sector information licensed under the Open Government Licence v3.0. Data: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero (© Crown copyright). Licence: Open Government Licence v3.0. Source: https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract. Source dates: Edition: Q2 2026; Release date: 2026-08-03; Latest record update in the file: 2026-07-24; Download date: 2026-08-25; Facts exported: 2026-10-18.
- Supported by National Energy SO Open Data. Data: Embedded Register, National Energy System Operator. Licence: NESO Open Data Licence v1.0. Source: https://www.neso.energy/data-portal/embedded-register. Source dates: Release date: 2026-10-10; Download date: 2026-10-13; Facts exported: 2026-10-18.
- Use of these registers does not imply endorsement by their publishers.
Source groups
| Group | Posts |
|---|---|
| Scotland Against Spin | 3 |
| Scottish Electricity Generating Stations | 1 |
Theme breakdown
| Theme | Posts |
|---|---|
| Onshore Wind | 3 |
What is the planning status of Golticlay Wind Farm?
No single status applies. Statuses by register record: Planning Application Submitted (2), Awaiting Consents (2), Under Construction (1), No Application Required (1), Scoping (1). The table gives each record's identifier, date and relationship; records are not combined.
What are the main community discussions around Golticlay Wind Farm?
4 archived public posts from 2 groups, dated 2026-02-22 to 2026-10-02. The most frequent theme tags are Onshore Wind (3). Post text is not reproduced here; each archive entry links to the post.
Archive entries
- 2026-10-02, Scottish Electricity Generating Stations · themes: Onshore Wind
- 2026-04-07, Scotland Against Spin · themes: none tagged
- 2026-03-25, Scotland Against Spin · themes: Onshore Wind
- 2026-02-22, Scotland Against Spin · themes: Onshore Wind