Arecleoch Wind Farm and extension
Arecleoch Wind Farm and extension is a wind, solar and storage project tracked on slava.it.com. The archive holds 2 community posts from 2 groups, latest 2026-10-02. 6 register records are listed (3 REPD, 3 NESO TEC). Their statuses differ, so no single status is given. Top recurring themes: Onshore Wind (1).
Facts and where they come from
Basis: register = taken from a public register (dates and licences are under Data credits).
Abbreviations: REPD = Renewable Energy Planning Database; TEC = Transmission Entry Capacity register; NESO = National Energy System Operator.
| Item | Value | Basis |
|---|---|---|
| Register records | 6 listed (3 REPD, 3 NESO TEC). Statuses: Scoping (2), Under Construction (2), Operational (1), Built (1) | register |
Register records
Each row is one register record with its own identifier; records are not combined. Relationships are stated only where a register links the records, and are otherwise labelled as unlinked or unverified. REPD dates are the record's update date and the date of the status event where one is recorded. The NESO files give no status date; the date shown is the MW effective-from date.
| Register | Identifier | Name as recorded | Status | Capacity | Date | Relationship |
|---|---|---|---|---|---|---|
| REPD | 3258 | Arecleoch Windfarm | Operational | 120 MW | record updated 2011-10-25; status event 2011-06-14 | Original wind farm; the name is spelled 'Arecleoch Windfarm'; no identifier is shared with the REPD NESO rows. |
| NESO TEC | PRO-000012-1 | Arecleoch | Built | connected 114 MW; cumulative 114 MW | no effective date in the file | Stage 1 of NESO project PRO-000012; relation to REPD 3258 is unverified (same site name, no shared identifier). |
| NESO TEC | PRO-000012-2 | Arecleoch | Scoping | connected 0 MW; cumulative 330 MW | MW effective from 2032-06-15 | Stage 2 of NESO project PRO-000012. |
| REPD | 6798 | Arecleoch Wind Farm (extension) | Under Construction | 72.8 MW | record updated 2025-07-25; status event 2025-06-01 | Extension: the REPD name is 'Arecleoch Wind Farm (extension)'. |
| REPD | 7882 | Arecleoch Wind Farm (extension) | Under Construction | 20 MW | record updated 2025-07-25; status event 2025-06-01 | Extension battery storage; REPD links it to 6798 (storage co-location). |
| NESO TEC | PRO-001111 | Arecleoch Extension Windfarm | Scoping | connected 0 MW; cumulative 72.8 MW | MW effective from 2026-08-31 | 'Arecleoch Extension Windfarm'; same capacity (72.8 MW) as REPD 6798 but no shared identifier, so the relation is unverified. |
Data credits
- Contains public sector information licensed under the Open Government Licence v3.0. Data: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero (© Crown copyright). Licence: Open Government Licence v3.0. Source: https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract. Source dates: Edition: Q2 2026; Release date: 2026-08-03; Latest record update in the file: 2026-07-24; Download date: 2026-08-25; Facts exported: 2026-10-18.
- Supported by National Energy SO Open Data. Data: Transmission Entry Capacity (TEC) register, National Energy System Operator. Licence: NESO Open Data Licence v1.0. Source: https://www.neso.energy/data-portal/transmission-entry-capacity-tec-register. Source dates: Release date: 2026-10-10; Download date: 2026-10-13; Facts exported: 2026-10-18.
- Use of these registers does not imply endorsement by their publishers.
Source groups
| Group | Posts |
|---|---|
| Scottish Electricity Generating Stations | 1 |
| Scotland Against Spin | 1 |
Theme breakdown
| Theme | Posts |
|---|---|
| Onshore Wind | 1 |
What is the planning status of Arecleoch Wind Farm and extension?
No single status applies. Statuses by register record: Scoping (2), Under Construction (2), Operational (1), Built (1). The table gives each record's identifier, date and relationship; records are not combined.
What are the main community discussions around Arecleoch Wind Farm and extension?
2 archived public posts from 2 groups, dated 2026-10-01 to 2026-10-02. The most frequent theme tags are Onshore Wind (1). Post text is not reproduced here; each archive entry links to the post.
Archive entries
- 2026-10-02, Scottish Electricity Generating Stations · themes: Onshore Wind
- 2026-10-01, Scotland Against Spin · themes: none tagged